  (A) Key Projects Milestones achieved

o  1st June 2007 - Project Started

o  December-2007 - Completed Study, Mapping, Configuring, customization, Training the Users and Testing the Application

o  January 2008 - Configured the Production Instance and loaded correct Master Data and GL 3 Years Historical Transactions

o  February 2008 – Open Balance Data and On Hand Inventory data provided and uploaded

o  March, 2008 -  AIG started using the application for completing the data entry for the year 2008


  (B) Additional tasks performed
 
o  Installed and implemented the latest release Release-12 and upgraded to 12.0.3 though.

o  The Actual Costing for Serial Number Item was found more crucial in the Business Process of AIG, a Critical customization was undertaken

o  Separate UAT instance configured due to change in the Chart Structure

o   Spent more time for Training and conducted additional training for SCM users

o  Incremental Data Loading, historical transactions migration also managed data exceptions

 

Most all the Business Process of AIG are mapped and configured within the Standard process of Oracle E-Business Suite. For customization we have followed Oracle standards and developed within the Framework and security of Oracle E-Business Suite.


  (C) List of Customizations and Workarounds

o   Inventory Landed Cost calculation Extension

o   Workaround solution for Project Nature Sales Transactions within the frame work of Oracle Finance and Distribution modules

o   Modified the FIFO Costing for Serial Numbered Items to use the Actual Cost

o   Form Personalization and Reports